|
CONSTRUCTION
EQUIPMENT GUIDE
Issue:
Midwest Edition • Publication Date: 11/23/2005
I-80
Interchange Gets Facelift in IA
By
Lori Lovely
Work
is wrapping up on a hot mix asphalt resurfacing project
in Davenport, IA, at the Interstate 80-U.S. 67 interchange
approaching the Mississippi River. The $5.2-million contract
was let in April, and McCarthy Improvement Company, the
winning bidder, started work in late May.
Founded
in 1897 as the McCarthy Stone Company, the Davenport-based
corporation put down its first asphalt paving in 1904. In
the past 100 years, the family-owned business has repaved
numerous air strips and interstates in the Midwest, southeast
and southwest.
“We’re close to being done with the project. The asphalt
work should be done by the end of August,” speculated Ron
Sines, McCarthy executive vice president, who anticipates
arrival of traffic signals currently on order by October
to complete the project. “The surface of I-80 is done, and
we’re already receiving positive feedback from commuters.”
He attributes the dry, albeit extremely hot, weather with
keeping work on schedule.
The
resurfacing is necessary due to the roadway’s age and heavy
usage. According to Mark Brandle, Iowa Department of Transportation
project manager, the Scott County roadway, one of the first
sections laid in Iowa when I-80 was started in the 1960s,
has never been totally reconstructed, and has been overlaid
only once in the past. An estimated 33,500 vehicles use
it each day, and he said 29 percent of that is truck traffic.
Adding the concrete base and the existing overlay, there’s
approximately 13 to 14 in. of existing pavement. Sines called
it “super elevation work,” using a wedge of dirt in the
median to fill in around the new overlays.
“The
problem with overlays,” Brandle said, “is that the slopes
get steeper and no longer meet federal guidelines. You have
to extend them, and to do that, you need more right of way.
It’s more economical to remove and replace them instead
of having to meet safety regulations when you extend them.”
He
added that enough right of way was purchased to accommodate
six lanes. “We have extra right of way,”Brandle
said.
The
work on Interstate 80 from 4 mi. west of the river entails
full-depth patching; pavement removal; milling a .5 inch
off the existing surface for resurfacing with 4 to 6 in.
of hot mix asphalt; grading; reconstruction of the Mississippi
River concrete bridge approach pavement; guardrail upgrades
and shoulder widening.
“We’re
widening because Iowa likes to put two to four feet of full-depth
paving into the shoulder, especially on interstates,” explained
Brandle.
That’s
thicker than they used to require, he said, because it helps
prevent ruts when motorists go off the edge.
“Maintenance
problems are eliminated with asphalt all the way out. It
holds up better,” Brandle added.
U.S.
67 and the interchange also will undergo full-depth patching
and hot mix asphalt resurfacing. Additional work includes
construction of additional turning lanes, removal and modification
of ramps and the addition of new traffic signals.
In
addition to widening the ramps, Sines said the ramps and
U.S. 67 intersection will be reconfigured.
“It’s
a major re-do,” he said.
After
tearing out deficient turning lanes and removing the “Y”
configuration, crews will construction on/off loops adjacent
to on/off ramps.
“It’s
a huge improvement to the configuration” that Sines believes
will increase safety.
Brandle thinks that by changing the traffic patterns and
removing the high-speed on- and off-ramps, safety will be
enhanced. Another safety improvement is the switch from
stop and yield signs to signals.
“The
intent behind the change is safety. There are a lot of collisions
now,” Brandle said.
Traffic
continues to be a challenge during construction. Despite
280 being offered as an alternate route, traffic remains
high on this section of road, still officially considered
rural, not urban.
“Traffic
is our biggest problem at the bridge,” reflected Brandle,
who added that it’s been difficult to predict rush-hour
flow. “It’s a half-cloverleaf design. There was a problem
with the eastbound on-ramp. Work went really fast. They
used new techniques to make sure the concrete cured fast.”
Despite
the implied urgency, Brandle said there’s been no shift
work. Crews are on site 10 hours a day, five days a week.
“We
weren’t anxious to do asphalt patching at night, and we’re
not comfortable doing inspections at night,” said Brandle.
Instead, he said it planned to expedite work during the
day. Besides, he added, “We didn’t want to complicate the
rental spec by doing night work.”
Because
traffic had to be maintained at all times, the State implemented
a relatively new lane rental specification. This developmental
incentive/disincentive program is uniquely set up: A specified
number of lane closure hours is allotted to the contractor,
after which the State charges the contractor $100 per hour
for lane closures. All lane closures are posted on the DOT’s
Web site and distributed in weekly press releases to keep
the traveling public updated.
Although
the bridge was a factor in the desire to limit lane closures,
Brandle said the program was politically motivated. Its
intention is to “make the contractor recognize in a different
way that we want to minimize lane closures. Aside from a
few contract issues that needed clarification, it’s working
well. It’s made them think; they opened up lanes to avoid
charges.”
Sines
is reserving judgment until the project is completed, but
as work progresses, he continues to evaluate whether the
new system puts the focus on what’s best for the company
as well as the overall project. Unlike early-completion
incentives, the lane rental spec offers the potential of
earning only a small amount of money, according to Sines.
However, other incentives might offset that lack of bonus.
McCarthy is on the “plus” side of smoothness incentives
(common to most Iowa interstate and primary roads contracts,
according to Sines).
“We’ve
earned incentives so far,” he said proudly. “We’re the leader
in the nation on this. It’s a quality issue, not a speed
issue. It forces you to produce higher quality roads to
get the incentives. It’s a good program.”
One
aspect of this project that might have slowed progress is
the fact that it involves a state border.
“We
have to coordinate with Illinois because it’s a border bridge,”
said Brandle. “There have been some issues with work across
the river on a rest area and a bridge rehab project. They
have lane closures in effect.”
Nevertheless,
said Sines, it has successfully coordinated with the Illinois
DOT to keep traffic flowing.
“It
went very well. We had ideal cooperation,” he said.
He
extended praise to the Iowa DOT, said “They’re top-notch
people who know their business. The traveling public doesn’t
realize what a good job they do maximizing tax dollars.”
Other
top-notch people Sines credits with the success of the project
include some of the subs on the job. Although he said there
hasn’t been a “huge amount of dirt removal,” Sines applauded
Foley Construction for the dirt work. G.M. Sipes completed
the patching; General Contractors worked on the bridge approaches;
All Iowa Contractors performed the striping; and Felco provided
traffic control. In addition, Davenport Electric Company
was responsible for electrical signalization work.
“They
took down the old lights and wired them to keep some going,
but their real work was with signalization,” said Sines.
“There’s a future plan for tower lights.”
Finally,
he paid tribute to the material itself as playing a significant
role in the project. “Asphalt has been around forever,”
said Sines, “but it’s an evolving technology. Research is
ongoing and the mix design continues to change. Material
selection is different. There’s more stringent testing of
aggregates. Asphalt is designed with heavy truck traffic
in mind now.”
Brandle’s
glad to see that. He said the I-80/U.S. 67 project was designed
to last 15 to 20 years, “unless there’s a big increase in
traffic.”
For
now, Sines promises commuters will notice a big difference
once the ramp overlay work is completed.
“It’s
a vast improvement to what was there before,” said Sines.
CEG
|