The $16.7 million Augusta Airport Taxiway project hit another Milestone date! Taxiway Charlie and Delta were officially opened in time for The Masters Tournament. Inclement weather has affected the progress from the start; however, due to determination, a lot of hours, pre-planning and effective implementation of the operations, the tasks necessary to achieve the goal were met.
As the Prime on this project, we are responsible for several key subcontractors, such as earthworks, electrical, HMA paving, and striping. Coordination of the subcontractors and completing the concrete pour sequence were paramount to this success. The airport has been supportive of alternate work plans to assist with the schedule as well. As a team, we are continuously seeking ways to be cost-effective and expedite the schedule to be fully complete.